King West Life – Occupancy Near Completion

p1

The occupancy phase at the East Liberty site in near completion: Tower 1 – the east tower (65 East Liberty St.) – all occupancy and Pre-Delivery Inspections (PDI) have been completed. Tower 2 – the middle tower (75 East Liberty St.) – all occupancy and PDI have been completed. Tower 3 – the west tower (85 East Liberty St.) – all 23 floors have … [Read more...]

Western Battery Site – Occupancy Started

t1

The occupancy phase at the Western Battery site has commenced. … [Read more...]

King West Life – Occupancy Started

King West Life

The occupancy phase at the East Liberty site has commenced: Tower 1 – the east tower (65 East Liberty St.) – all 23 floors have been completed. Windows installation and exterior finishing work has been completed, with occupancy reaching the 16th floor and Pre-Delivery Inspections (PDI) reaching the 20th floor. Tower 2 – the middle tower (75 East Liberty … [Read more...]

Western Battery Site – Construction Update

Construction update - Dec 18, 2012

The construction at the Western Battery site is continuing as planned - all 26 floors have been completed. Some mechanical work is still required on the rooftop, windows installation and exterior finishing have extended passed 18th floor. … [Read more...]

King West Life – Construction Update

LV1

The construction phase at the East Liberty site continues: Tower 1 – the east tower (65 East Liberty St.) – all 23 floors have been completed. Windows installation and exterior finishing are nearly completed, with work shifting to the interior finishing. Tower 2 – the middle tower (75 East Liberty St.) – all 25 floors have been completed. Some … [Read more...]

Western Battery Site – Construction Update

T1

The construction at the Western Battery site is continuing as planned and has reached the 25th floor with exterior finishing work and windows installations commencing at the base of the tower. … [Read more...]

Western Battery Site – Construction Update

T1

The construction at the Western Battery site is continuing as planned and has reached the 15th floor. … [Read more...]

King West Life – Construction Update

LV2

The construction phase at the East Liberty site continues: Tower 1 - the east tower (65 East Liberty St.) - 23 floors have been completed, windows installed and exterior finishing Tower 2 - the middle tower (75 East Liberty St.) has reached 25th and final floor. Window installation and exterior work has reached 11th floor Tower 3 - the west tower (85 East … [Read more...]

Western Battery – Construction Update

5

The construction phase at the Western Battery site is progressing as planned and has reached the 5th floor  - the precast panel assembly continues. … [Read more...]

King West – Construction Update

1

The construction phase at the East Liberty site continues: Tower 1 - the east tower (65 East Liberty St.) - 23 floors have been completed and windows installed, exterior finishing work has extended above 11h floor Tower 2 - the middle tower (75 East Liberty St.) has reached 19th floor with windows being installed at the podium level Tower 3 - the west tower … [Read more...]